    Advanced Production Control - Dashboard and KPIs
    In This Topic

    End of shift work space

    Through configuration, a work space with tiles and lists can be setup that provides a good overview of production status of the past day, running issues etc. Examples of relevant tiles:

     

    Production KPIs

    Production summary

    Production control > Inquiries and reports > Production summary 

    Summary screen that shows the total quantities, planned and actual lead times and delays (if any) per production order.

    Group data per period or create tiles with e.g. orders ended yesterday, day before yesterday.

    Field Description Remark
    Production Production order

    Item number

    Released product

    Name

    Product name

    Site

    Warehouse

    Status

    Production status

    Quantity

    Scheduled quantity

    Good quantity

    Good RAF quantity

    Error quantity

    RAF error

    Delivery

    Planned delivery date

    Ended

    Actual end date

    Delayed production

    Days delay

    Planned lead time

    Planned cycle time [s]

    Seconds between Scheduled start time first operation and Scheduled end time last operation

    Lead time

    Cycle time [s]

    Sceonds between Actual process start time and Actual process end time

     

    Resource utilization

    Resource utilization colors

    Production control > Setup > Resources > Resource utilization colors

    Button Create deafult setup. The default utilization colors range from pale green (low utilization) to green (>90% utilization), yellow (>100% utilization), orange (>110% utilization) and red (>120% utilization).

     

    Capacity load

    Production control > Setup > Resources > Resource groups / Resources > Button Capacity load

    The utilization is calculated automatically, and the corresponding color is displayed.

    Field Description Remark
    Utilization Scheduled utilization rate %